Project Overview
The San Dieguito Lagoon project area covers approximately 154 acres of land east of I-5 and adjacent to the San Dieguito River. It serves as a critical habitat for migratory waterfowl and sensitive bird species, provides essential nursery grounds for coastal fisheries, and creates a buffer against flooding and sea level rise.
Phase 2 of the project serves as mitigation for the North Coast Corridor (NCC) program—a joint effort between SANDAG and Caltrans—and the City of San Diego’s El Camino Real Bridge and the San Dieguito River Park Coast to Crest Trail projects.
The project accomplished three primary objectives:
- It created and restored wetland habitat by establishing approximately 64 acres of tidal salt marsh and 15 acres of brackish wetlands and enhancing an additional 5 acres of riparian habitat.
- It protected against future sea level rise and floods by creating a sustainable system that provides transitional habitat between the restored salt marsh and the existing San Dieguito River channel.
- It improved trail connectivity and public access by creating a new trail along the southeastern edge of the project area, parallel to El Camino Real, that links to the Dust Devil Nature Trail at the southern end and (will eventually link) to the Coast to Crest Trail at the northern end.
Project Partners
- 22nd Agricultural District
- Caltrans
- City of Del Mar
- City of San Diego
- San Diego Gas & Electric (SDG&E)
- San Dieguito River Park Joint Powers Authority
- Southern California Edison (SCE)
Schedule
In partnership with the San Dieguito River Park Joint Powers Authority, we began construction on Phase 2 of the San Dieguito Lagoon Wetland Restoration project in 2022. This work is expanding and enhancing the efforts of Southern California Edison (SCE), which began restoring wetlands in the lagoon in 2011 (Phase I).
We completed construction on this project in 2024. SANDAG and Caltrans are currently overseeing the long-term monitoring of the project through 2034.
Budget
This project was funded primarily by TransNet with some federal funding.